    December 2023 Construction Updates

    Exciting Milestones Reached in Elana Place Construction

    Moving on to Stage 2, we have completed the sewer, drainage, and water components, with roads built to the base course levels and kerb crews on site. Before the end of the year, our goal is to lay the first asphalt layer, make significant progress on electrical assets, and finalise the shaping of the Wetland.

    We are thrilled to provide the team with an update on the significant progress of civil works at Elana Place.

    This marks an opportune moment for buyers to commence the finalisation of their finances. We are committed to providing further updates in early 2024, regarding preparation for settlement.

    Anticipating the completion of Stage 1 in early 2024, Stage 2 is expected to follow shortly thereafter.

    Captured in the latest aerial photographs above, the ongoing construction at Elana Place reveals a significant transformation, with the site now evolving into a nearly finished development.

    In Stage 1, all groundwork has been successfully completed, and essential assets are currently undergoing testing. Over the next couple of weeks, the contractor will focus on concrete footpaths/driveways, topsoiling, and placing the final layer of asphalt.

    Elana Place is Your Place for Everything.

    Talk to our friendly Estate Manager, Shaunna Britee, on 1300 001 998 or email us at [email protected]

    View our land available now on: https://elanaplace.com.au/land-for-sale/

    News detail

    Recent Articles

    News

    Stages 1 & 2 Nearing Completion

    For Stage 1, we’re thrilled to announce that civil works are complete. The only outstanding authority to achieve Statement of...

    Read More
    News

    Stage 1 Valuation Access

    We have allocated another day for on-site valuations for all the people who missed out previously. Our Project Management Team...

    Read More
    News

    February 2024 Construction Updates

    We are pleased to advise that Stage 1 at Elana Place is nearing completion, with construction works on target to...

    Read More
    News

    December 2023 Construction Updates

    Exciting Milestones Reached in Elana Place ConstructionMoving on to Stage 2, we have completed the sewer, drainage, and water components,...

    Read More